Design + Technology + Organization = Piled Foundation for Production Hall in Janowiec Wielkopolski
20-06-2017
Owing to a good solution, namely the proper choice of technology and perfect organization of piling works, we were able to construct piled foundation for a three bay production hall and warehouse (60x72m) in just 5 days. Precast reinforced concrete piles were applied, with some of them installed in close proximity to the existing buildings. See the video which shows all the advantages of the driven precast pile technology.